Madrid - Valladolid Line
European financing
EUROPEAN UNION

During the period 2000-2006 co-financing was provided as follows:
- from the Cohesion Fund for track bed works on the Madrid – Valladolid (Valdestillas) section, with funding of 1,573.7 million Euros;
- from the European Regional Development Fund (ERDF) for the track and facilities (electrification, signalling and communications) on the Segovia – Valladolid (Valdestillas) section, with funding of 193.3 million Euros;
- from TEN-T (Trans-European Transport Network) funds, which provided 20.6 million Euros for studies and projects, and for track-bed and track works, on the Valdestillas – Río Duero section.
During the period 2007-2013 co-financing will be provided as follows:
- From the Cohesion Fund as part of the Operational Programme of the ERDF Cohesion Fund, with estimated funding of 177.5 million Euros for various track-bed, track and facilities works.
- From the European Regional Development Fund (ERDF), as part of the Operational Programme of Castile-León, with estimated funding of 66.8 million Euros for various track-bed, track and facilities works.
(Data as of 30 June 2011)
European Investment Bank (EIB)

The European Investment Bank (EIB) collaborates in the funding of this project.